正规的棋牌平台排行榜

项目

雷尼尔山海滩

雷尼尔海滩高中替换项目

项目简介

雷尼尔海滩高中 will be replaced with a new four-story high school of approximately 297,000平方英尺. When completed, it will provide permanent space for 1,600 students grades 9-12. 在分阶段施工期间,学生将留在现场. A regional 技术中心 is being incorporated into the project as well as a district data center. The project is being built with aspirations of a LEED Platinum certification.

资金来源: 由卓越建筑及基建征款资助, 由西雅图选民于2019年批准的, 技术, 及学术/体育V资本征款(btav), 由西雅图选民于2022年批准.

You can contact SPS in your own language through the online feedback form

时间轴

construction phase graphic showing that the school is in the Construction phase
了解每个项目阶段
  • 预设计阶段完成
  • 方案设计阶段完成
  • 设计开发阶段完成
  • 施工文件/许可阶段正在进行中
  • 投标和授予阶段完成
  • 分期建设:2022年4月至2026年12月
    • 第三期工程正在进行
    • 预计到2025年1月,70%的新建筑将搬进西部
    • Phase 4, construction of Performing Arts building expected completion June 2026
    • 第五阶段,现场安装预计于2026年12月完成.

项目设计

新学校的建筑师效果图

drawing of a large three story building with a walkway leading to it between trees
新增主入口
包括建筑物和运动场的场地平面图
更换工程的地盘平面图
室内走廊的绘图
剧院大堂
画一个体育馆,有露天看台,橙色和蓝色的口音
体育馆
公共区域的绘图,窗户从上面的楼层向外看
餐厅朝向健身房
large common area with dining tables and stairs; a room with glass windows looking out toward below says LIBRARY
图书馆及公共餐厅
一幢大楼前的田径场地图
田径
drawing of a small group area with a room next to it that has blue walls
4楼小团体区
有栏杆的走道,可以看到下面的地板
4楼公共场所向下看
一个有座位和壁画的开放空间
3楼东公地
画一个有书架和座位的图书馆
图书馆位于二楼
带午餐桌的公共餐厅图
一楼用餐区

项目进展

进度更新公布了前一个月.

2024年3月

主楼屋顶现已完工. All the other construction work continues including exterior metal wall framing and window installation. The interior spaces are starting to take shape with metal wall framing, 绝缘, 还有公用事业.

同样的工作将在4月份继续进行.

实时网络摄像头和项目进展照片

查看网络摄像头以查看项目现场.

这些幻灯片展示了工程的施工过程.

一个小建筑前面的建筑碎片和灯杆
第二阶段-拆除看台- 2022年夏季
有立管的大房间中间有建筑碎片
Phase 2 – Demolition to create a temporary locker room for use during construction – Summer 2022
建筑物前面的施工设备
第二阶段-选择拆除现有建筑物- 2022年夏季
一辆装有高钻的卡车,人们正在工作
Phase 1 – Installing geothermal wells for heating and cooling – Summer 2022
一个钻井平台矗立在一片覆盖着稻草的泥土上. 照片里有卡车
在现有棒球场钻地热井- 9月. 2022
一个人站在战壕里,战壕附近有一个梯子
连接位于地下的地热井
卡车上挂着高大的东西,停在泥土地里
开始安装夯集料墩- 10月. 2022
一个大型框架正在一个有大块岩石的地区安装
安装临时建筑帐篷- 12月. 2022
a tall drill machine with a person in a hard hat stands in a muddy field
地热井继续安装- 12月. 2022
在一个有灯的巨大帐篷下,金属雕塑矗立在泥土的边缘. 建筑工人正在使用设备
深埋地下公用设施的挖沟和粗加工- 1月. 2023
yellow mesh covers some areas of a gavel covered ground next to canvas walls
东电气室未来位置- 2月. 2023
一个钢筋笼的巨大分布,工人们在添加更多的钢筋
钢筋用于混凝土板基础
混凝土搅拌车在泥坑间的车道上排成一排
42 cement trucks delivered about 415 cubic yards of concrete – April 5, 2023
two cement mixer trucks are backed into openings in a large white tent
2023年4月5日,两辆卡车同时开进帐篷
a worker in a safety vest and hardhat is smoothing concrete in a large flat area
2023年4月5日,混凝土浇筑后必须平整
在一个大帐篷下, white waterproofing material has a stack of electrical conduit placed in a guie frame with rebar beneath it
Waterproofing, rebar, and electrical conduit for inside of concrete slab foundation – March 2023
大帐篷下混凝土框架内的钢筋网格
2023年4月为4A席板准备混凝土
工人们在一个大帐篷下面的坑里安装钢筋
Placing rebar and utility conduit on the waterproof membrane April 2023
底部是钢筋网格, 一群头戴安全帽、身穿安全背心的工人站在中间, a concrete pump is in the back with a large tent structure over it all
浇筑额外的基础垫板- 2023年5月
rebar formed into tall grids sits in foreground on top of a white material. 背景是一个大帐篷
2023年5月为另一个基础垫板安装钢筋
一台起重机正在从管道结构上吊起一个大框架
拆除施工帐篷- 2023年5月
一个钢架正在混凝土地板上搭建. 左边有一只鹤
Steel erection began on the east part of the new school – August 2023
a steel frame has a large delivery trailer in front of it with bent steel on it
Steel erection underway with steel stair sections being delivered – August 2023
有起重机的建筑物的钢框架
Four floors of steel erected; new gym will attach to this structure – Sept. 2023
一栋在建的楼,住着几个人
在金属甲板上铺设混凝土板- 9月. 2023
A group of men in orange vests and helmets working on a construction site
技能中心大楼的启动屋顶- 9月. 2023
a four story steel frame for a large building with construction cranes, lifts, and other machines
South side of new 4-story classroom building which will overlook the football field – Oct. 2023
一座大型钢结构建筑的金属框架正在进行中
Exterior metal framing on Skill Center part of classroom building – Oct. 2023
a concrete truck is pumping concrete to the third floor of a steel framed four-story building under construction
在3楼金属甲板上浇筑混凝土- 10月. 2023
一个大平面的背景上有一个起重机, 工人们四处分散, 还有很多橙色建筑标准
屋顶上的工作正在进行- 10月. 2023
建筑被白色材料包裹着,上面有一个洞作为门.
Skills center building wrapped in weatherproofing to allow exterior work to continue – Nov. 2023
在一栋还没有围墙的在建大楼里
Installing light gauge metal stud framing and hollow metal door frames – Nov. 2023
two workers in construction safety equipment are on a lift holding green sheets of material against studs
防水墙板开始放置- 11月. 2023
建筑工地上,一座四层楼高的钢框架拔地而起
教室钢结构和金属甲板完成- 12月. 2023
a four story frame of building has part of it wrapped in white material at a muddy construction site
Exterior metal stud framing on the north side of the classroom building – Dec. 2023
two workers on a lift are moving green wallboard into place on steel frames on an indoor construction site
石膏墙板安装- 12月. 2023
a concrete floor with steel framing and a view out the side showing it is up high
四楼金属甲板混凝土板完工. 2023
looking out through structural steel framing with metal studs on a building under construction
体育馆外部金属框架安装- 2月. 2024
正在建造的建筑物中正在建造的大楼梯
穿过中庭的中央楼梯部分之一. 2024
a two story interior space under construction with large pipes in the ceiling
技能中心航天金属车间空间- 2月. 2024
a room with a window has wallboard that is taped but not painted and construction equipment in the room
1楼教室准备油漆底漆- 2月. 2024
exterior of a 2, 3, and 4 story building under construction with materials in the foreground
南面向东的景色- 2月. 2024
a 4-story building under construction has metal framing and the bottom floor has yellow sheathing
新大楼南侧——2024年3月
用金属框架建造的建筑物内部. 金属管道件堆放在地板上
Interior framing continues, looking into main building from gymnasium – 2024年3月
a room with two large windows is under construction with pink 绝缘 around the windows and metal framing on the right wall
正在进行的教室- 2024年3月
a four story building under construction with metal framing and some yellow wall covering. 可以看到两部电梯和工人
新建筑西侧的外部框架- 2024年3月

社区参与

学校设计谘询小组(SDAT)

在设计过程的早期, representatives from the school community come together to form a school’s SDAT. SDATs typically include school and district staff, parents, students, and community members. 项目施工经理也参与其中. Due to the timing of the 雷尼尔山海滩 SDAT, meetings were held virtually. 阅读更多内容并回顾会议记录.

项目团队

设计公司: 巴塞蒂建筑事务所/穆迪·诺兰

项目管理公司: 拟基本解

总承包商: Lydig施工

正规的棋牌平台排行榜

让我们来谈谈评论和问题表格

拟基本解经理: 保罗•波波维奇 ppopovich@parametrix.com, 253-208-7831

雷尼尔海滩高中
苏厄德公园大道8815号. S
西雅图,华盛顿州98118

学校的网站

学校简介